2009.04 pumpstation 11

pumping station, wet wells, generators and creek landscape integration

crispin schurr design architect at ccc

programme

  • terminal station for gravity fall western interceptor foulwater pipeline

  • subgrade wet well collection / pumping chamber

  • generator building

  • substation and switching rooms

  • crane and storage

issues

  • restricted site area

  • creek flowing along boundary

  • residential sites to all sides

  • two generator engines at over 120db each

  • little public green space in area

solutions

  • masterplanning of entire site

  • location of generator building as far from all residences as possible

  • vertical concrete maze for airflow into generator building

  • robust concrete construction expressed with relief

  • high level toughened glazing for security & vandal prevention

  • timber slatted cladding difficult to graffiti & incorporates warmth

  • metal planted arbor creates layer of colour and softness to hard building materials

  • park environs create pocket park

  • positive urban design creates community ownership, reduces vandalism

status

  • completed

awards

  • nzia resene colour award

  • nzia local architecture award

  • nzia national architecture award

  • nzia new zealand architectural medal finalist